Global AI companies need more computing capacity than their usual hubs can supply quickly, and India is one of the places they are looking. The Times of India reported on October 26 that operators say delays in securing power and capacity elsewhere are pushing some AI firms to spread infrastructure across countries. This article puts numbers on India’s side of that story and separates what is operating from what is only planned.
The numbers
Cushman & Wakefield’s India Data Centre H1 2026 update is the most detailed recent source. It covers the top seven markets:
| Measure | H1 2026 |
|---|---|
| Operational capacity | 1,789 MW (about 1.8 GW) |
| Added in H1 2026 | 178 MW |
| Pipeline to 2030 | 3,860 MW: 509 MW under construction, 3,351 MW planned |
| Facilities and operators | 147 facilities run by 33 providers |
| Capital needed through 2030 | $29.9 billion |
By city, Mumbai leads with 890 MW operational, about half the national total, followed by Chennai (214 MW), Delhi NCR (183 MW) and Hyderabad (151 MW), according to figures reported from the same update. Cushman & Wakefield says operational capacity has risen from about 400 MW in 2019, and ranks India third in Asia-Pacific.
Other sources use different measures. One government-linked figure puts installed data centre power at about 1.57 GW in August 2026, which does not match C&W’s 1.789 GW because the two count different things. Always check what a capacity figure includes before comparing.
The pipeline is mostly not built yet
The headline is the 3.9 GW pipeline. But only 509 MW of it, about 13% by simple division, was under construction when the report was written. The remaining 3,351 MW is in planning. New facilities need land, grid connections, equipment and customers before they count as capacity.
Projects reported in secondary coverage include a planned 1 GW AI data centre in Visakhapatnam by Google with AdaniConneX and Nxtra, and a planned campus of up to 1 GW in Hyderabad by TCS. Treat these as announced plans, not operating capacity.
Who is driving demand
According to figures in a Cushman & Wakefield-based Invest India document, hyperscalers accounted for more than 80% of data centre absorption in H1 2026. JLL’s data, reported by Construction Industry Today, shows 101 MW absorbed in H1, more than 20% above its three-year average, with 82% of it pre-committed hyperscale capacity. This means large cloud providers book capacity before it is built, which supports investment but also means smaller Indian companies may find less available.
The Economic Times reported in July that “neocloud” providers such as CoreWeave, Together AI, Nebius, Lambda Labs, Crusoe and Nscale were in talks with Indian operators about leasing capacity for AI inference, meaning running trained models for users. Talks do not guarantee deals.
Why power is the real test
AI changes what a data centre has to deliver. Construction Industry Today reports that AI racks draw 50 to 60 kW, compared with 8 to 12 kW for traditional cloud racks, and that top-tier (Tier IV) facilities made up 43% of new supply in H1 2026, up from 21% in 2024.
One analysis from RESI India describes power demand as the binding constraint. It estimates data centres used about 0.5% to 1% of India’s grid electricity in 2025 and could use 2% to 8% by 2030 to 2032 in higher-growth scenarios. These are projections from a single analysis and depend on how fast capacity is built.
Cooling and water matter too, and use varies a great deal by design. Direct-to-chip liquid cooling and closed-loop systems are being adopted to manage heat, but water-use practices differ by operator and site.
Why India is attractive, and where it could fall short
The case for India is a large digital economy, a mature technology services sector, connectivity hubs in Mumbai, Chennai, Hyderabad and Bengaluru, and policy support. Data centres have infrastructure status, and the Union Budget 2026–27 was reported to include a tax holiday until 2047 for eligible foreign cloud providers using Indian data centres, subject to conditions. Confirm the details with the official Budget documents before relying on this.
Tax benefits alone don’t build a facility. Operators also need reliable power, land, network connectivity, approvals and skilled staff. Capacity is also concentrated: Mumbai alone holds about half of operating capacity.
What this means for readers
This section is our analysis.
- Businesses and startups: More local capacity could improve access to cloud and AI services, but hyperscaler pre-commitments mean availability and price for smaller buyers aren’t guaranteed.
- Job seekers: None of the sources we reviewed gave reliable job estimates. Construction, electrical and cooling work are likely to see demand, but data centres run with comparatively small operating teams.
- Citizens and policymakers: Grid reliability and water use will decide whether the boom is sustainable, so watch for transparent reporting on both.
What to watch
- How much of the 3,351 MW in planning moves into construction.
- Whether power connections and cooling keep pace with the new builds.
- Whether neocloud talks turn into signed leases.
- Colocation vacancy, which one source puts at 14.9% in H1 2026, as a sign of whether supply is meeting demand.
SOURCES AND FURTHER READING
- India Data Centre Market H1 2026, Cushman & Wakefield
- India’s Data Centre Pipeline Reaches 3.86 GW as AI Drives Growth, Voice&Data
- India’s Data Centre Capacity Reaches 1,789 MW in H1 2026, Construction World
- India’s Data Centre Growth Story: Expansion, Investment and Economic Opportunity, Invest India (Cushman & Wakefield data)
- Data Center Setup in India: Power, Cooling, Connectivity, and Site Selection, Construction Industry Today
- India’s Data Centre Market: A Strategic Analysis, RESI India
- India’s AI data centre map, Safeguard
- India’s $67B Data Centre Boom, DMC Education

0 Comments