AI Data Centres vs Local Water and Power: India’s Test

By Dileep solanki | Published: October 22, 2026 | Updated: November 13, 2026

India wants to be a major home for AI computing, and global companies are planning large data centres to match. But a data centre is not a cloud. It is a building that needs round-the-clock electricity, cooling and land, often in cities that are already short of water. This article looks at where that tension is showing up, what India’s planning think tank has now asked states to check, and what remains uncertain. For capacity figures and the project pipeline, see our separate article on India’s data centre boom.

A protest near Mumbai

A Reuters investigation published on October 9 describes residents in Thane, near Mumbai, objecting to an Amazon data centre planned on a 54-acre site close to their homes. On September 8, hundreds of residents gathered by the site with placards, and Reuters reports that more than 1,000 residents say the project was pushed through without meaningful consultation. Their worries are the strain on local power and water supplies and noise that could harm children and the elderly. Reuters says it interviewed more than two dozen residents and reviewed official correspondence.

Amazon told Reuters the facility will use water-free cooling and a dedicated power supply separate from homes, along with noise-mitigation measures, and that it is drawing up community outreach plans. The project is part of Amazon’s planned US$21 billion investment in AI infrastructure in India by 2030.

Industry voices are not uniform. Reuters quotes Sharad Agarwal, CEO of Sify Infinit Spaces, which runs 14 data centres, saying he would never build one in a residential area, because such sites need abundant, uninterrupted power and water that could be scarce near homes. The government has defended data centres publicly, promoting them as “the invisible engines powering India’s digital life” and arguing that modern technology uses water and electricity more efficiently.

A similar dispute in Andhra Pradesh

According to Reuters, environmentalists are opposing Google’s $15 billion data centre project in Andhra Pradesh, citing risks to wildlife, water and power supplies. They also allege that a temple’s land was used without permission. Those are allegations, and we have not seen a response from the project’s backers on that point. Earlier coverage from February said the state government has accounted for the electricity and water demand and plans to use surplus monsoon water that otherwise drains into the Bay of Bengal.

How big is the resource question?

The figures vary by source, so it is worth seeing the range. NITI Aayog framework coverage puts India’s installed data centre capacity at about 1.57 GW in August 2026. According to the Council on Energy, Environment and Water (CEEW), as reported by Communications Today, data centres consumed about 13 terawatt-hours of electricity in 2024, roughly 0.8% of national demand, and that could rise nearly fivefold to 57 TWh by 2030, about 2.6% of demand. Another summary says 1% to 2%, so the share should be confirmed from CEEW’s own data.

On water, secondary summaries of the CEEW and NITI material say Indian data centres used about 150 billion litres in 2024-25. S&P Global, cited by Reuters, estimates that 60% to 80% of Indian data centres could face high water stress this decade. A CEEW and WRI India assessment, according to one secondary summary, found that more than 75% of 278 data centres sit in areas with high or extremely high water stress, mostly in Mumbai, Chennai, Bengaluru, Hyderabad and Delhi-NCR. One summary also says a 100 MW data centre uses about 2 million litres of water a day, although actual use depends heavily on the cooling design.

Why cooling choices matter

This explanation is general, not specific to any project.

Evaporative cooling uses a lot of water but less electricity. Air cooling and closed-loop liquid systems use little or no water but typically need more electricity. A claim of “water-free cooling” therefore solves one problem and may add to another, which is why power and water plans must be reviewed together. Companies’ statements about their own designs are claims until independent data on actual use is published.

What NITI Aayog now asks states to check

On October 14, NITI Aayog’s Frontier Tech Hub, with Deloitte India, released a Data Centre Evaluation Framework. It is non-binding guidance, and states still make the final decisions on land, water and power. It organises assessment into five areas: power and energy, water and cooling, siting and environmental sustainability, economic and strategic value, and governance and implementation.

According to coverage by ThePrint and others, the framework asks states to approve projects only after grid, water and land capacity for the entire campus has been verified. Developers, distribution companies and state transmission utilities should jointly validate a power plan that covers year-by-year energisation and substation upgrades. States should prepare 20- to 30-year seasonal water-availability assessments and protect existing water users, and they should designate “red zones” where data centres should be restricted because of hazard exposure, water stress, land-use conflicts or inadequate infrastructure. The framework also asks states to calculate each project’s net fiscal contribution after concessions on land, stamp duty and electricity duty, and says developers should fund grid assets built exclusively for their projects.

A secondary summary of CEEW’s policy mapping says 15 states have data centre or IT policies, but only five include explicit sustainability norms. We could not confirm this against CEEW’s own document.

Our reading

This section is analysis.

The framework addresses exactly the gaps the Thane dispute exposes: whether resources are verified before approval, and whether affected residents are consulted. But it is guidance, not law, and the coverage we reviewed gives no timeline for adoption. The practical test will be whether states use it before approving large campuses.

Questions worth asking about any local project

A resident, journalist or local official can ask a handful of plain questions. Has a seasonal water assessment been published, so it is clear that supply was checked before approval? Who pays for new substations and grid lines, since that determines whether households end up subsidising the project? Is the cooling design stated, along with expected water and power use, so the claims can be checked later? Was there public consultation before approval, which is the point the Thane residents dispute? What are the noise limits and backup power arrangements, since these affect neighbours directly? And will the operator report actual water and power use once the facility is running, which turns promises into measurable results?

What to watch

Watch whether states adopt the NITI framework and publish red zones, and how the Thane and Andhra Pradesh disputes are resolved. Independent data on actual water and electricity use by operating facilities would also help settle the argument. Some reports say India is preparing a national data centre policy, but we did not confirm that from an official source.